Solar (GES) Application

Information and documents required for unlicensed electricity generation connection applications.

All applications (1–9)

  1. Unlicensed Generation Connection Application Form (Regulation Annex-1)
  2. Authorisation documents of the persons authorised to represent and bind the legal entity
  3. Documents showing the direct or indirect shareholders of the legal entity and any control relationship
  4. For the site of the plant: title deed, a lease of at least two years with signature circular/declaration attached, or a document proving the right of use
  5. For non-rooftop applications, a document from the Ministry of Agriculture and Forestry or its provincial directorate confirming the site does not include absolute, special-crop, planted or irrigated agricultural land, or land that would disrupt agricultural use
  6. Information on consumption facilities: unique code for existing facilities; for planned facilities, a building permit under Zoning Law No. 3194 (or equivalent) and an approved electrical project cover page
  7. Except for rooftop installations, the document required under the EIA Regulation for projects above threshold values
  8. Receipt showing the application fee was paid to the relevant network operator
  9. Single-line diagram showing the technical specifications of the planned facility

Additionally for wind and solar (10–12)

  1. Technical Evaluation Form in the format of the General Directorate of Energy Affairs (also on CD in Excel format)
  2. Coordinated site plan approved by LİHKAB or a licensed surveyor
  3. Declaration under paragraph ten of Article 37 of the Regulation (Annex-1)

Cogeneration applications (13)

  1. Document on the facility's total efficiency

Renewable sources (14)

  1. Document proving the right to use the source. Not required for wind, solar, biomass and biogas plants; geothermal and hydro sources require the relevant licence or approval.

Originals or notarised copies must be submitted. Photocopies must be marked "Original seen", with the name and signature of the authorised person. The network operator may not reject an application for missing documents not on this list.